Use the following attached data for problems 43-45 (all times are in days)

Use the following attached data for problems 43-45 (all times are in days)

 

1)     What is expected completion time for activity D?

A.   12.000

B.    12.667

C.    12.333

D.   13.152

 

 

2)     What is the variance for activity A?

A.   1.000

B.    1.361

C.    5.444

D.   4.315

 

 

3)     The critical path is: A, B, D. What is the probability of completing the project in less than 26 days?

A.   0.2190

B.    0.4516

C.    0.7125

0.1245