Thabo Mbeki president of Mbeki construction, has developed the task, durations and predecessor relat

FIRST GRADER essay writing company is the ideal place for homework help. If you are looking for affordable, custom-written, high-quality and non-plagiarized papers, your student life just became easier with us. Click the button below to place your order.


Order a Similar Paper Order a Different Paper

Thabo Mbeki president of Mbeki construction, has developed the task, durations and predecessor relationship in the following table for building new models. Draw the AON network and answer the questions that follow.

Time estimates (In weeks)

Activity

Immediate Predecessor(s)

Optimistic

Most likely

pessimistic

A

4

8

10

B

A

2

8

24

C

A

8

12

16

D

A

4

6

10

E

B

1

2

3

F

E,C

6

8

20

G

E,C

2

3

4

H

F

2

2

2

I

F

6

6

6

J

D,G,H

4

6

12

K

I,J

2

2

3

a. What is the expected (estimate) time for activity C?

b. What is the variance for activity C?

c. Based on the calculations of estimated times, hat is the critical path?

d. What is the activity variance along the critical path?

e. What is the probability of completion of the project before week 36?

Please answer d and e only. Thanks